[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113964":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113964,787,2,"多选题","在电缆敷设过程中，应做的工作包括（）。2011",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","标明电缆型号",true,{"key":16,"text":17,"correct":14},"B","排列整齐",{"key":19,"text":20,"correct":21},"C","避免平行重叠",false,{"key":23,"text":24,"correct":14},"D","横平竖直",{"key":26,"text":27,"correct":14},"E","标明起讫地点","ABDE","考查内容：输配电线路的施工方法。电缆敷设中应及时整理，做到横平竖直、排列整齐，避免交叉重叠。及时在电缆终端、中间接头、电缆拐弯处、夹层内、隧道及竖井的两端等地方的电缆上装设标志牌。标志牌上应标明电缆线路的编号、电缆型号、规格与起讫地点。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]