[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113957,787,2,"多选题","工业机电设备负荷联动试运转中，主要考核的内容有（ ）。2019",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","安装质量",true,{"key":16,"text":17,"correct":14},"B","设备性能",{"key":19,"text":20,"correct":21},"C","自控功能",false,{"key":23,"text":24,"correct":14},"D","生产能力",{"key":26,"text":27,"correct":14},"E","生产工艺","ABDE","负荷联动试运转是在投料的情况下，全面考核设备安装工程的质量，考核设备的性能、生产工艺和生产能力，检验设计是否符合和满足正常生产的要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]