[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113917":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113917,787,2,"多选题","建设单位接受施工单位对分部工程报验申请后应组织（ ）等单位有关项目负责人及技术负责人进行验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工",true,{"key":16,"text":17,"correct":18},"B","质监",false,{"key":20,"text":21,"correct":14},"C","监理",{"key":23,"text":24,"correct":18},"D","主管",{"key":26,"text":27,"correct":14},"E","设计","ACE","2020版教材P361 施工单位专业技术质量负责人进行验收。（二）分部工程质量验收组织分部（子分部）工程应在各分项工程验收合格的基础上，由施工单位向建设单位提出报验申请，由建设单位项目负责人（总监理工程师）组织施工单位和监理、设计等有关单位项目负责人及技术负责人进行验收。 （三）单位工程质量验收组织单位（子单位）工程完工后，由施工单位向建设单位提出报验申请，由建设单位项目负责人组织施工单位、监理单位、设计单位、质量监督部门等项目负责人进行验收。 `",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]