[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113899":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113899,787,2,"多选题","临时用电的用户，应安装用电计量装置。对不具备安装条件的，可按（ ）计收电费。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","用电电压",false,{"key":16,"text":17,"correct":18},"B","用电容量",true,{"key":20,"text":21,"correct":18},"C","使用时间",{"key":23,"text":24,"correct":18},"D","规定的电价",{"key":26,"text":27,"correct":14},"E","用电次数","BCD","2020版教材P340 本题考查的是建设用电的规定。临时用电的用户，应安装用电计量装置。对不具备安装条件的，可按其用电容量、使用时间、规定的电价计收电费。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]