[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113898":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113898,787,2,"多选题","在电力设施保护区内进行大件吊装或卸载，制定施工方案前先要摸清周边电力设施的实情，例如（ ）等。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","地下电缆的位置",true,{"key":16,"text":17,"correct":14},"B","地下电缆的标高",{"key":19,"text":20,"correct":14},"C","空中架空线路的高度",{"key":22,"text":23,"correct":14},"D","空中架空线路的电压等级",{"key":25,"text":26,"correct":27},"E","该电力保护区的主管单位",false,"ABCD","2020版教材P344 （1）发生在电力设施保护区内安装作业，主要是开挖地下管沟和大件吊装或卸载，以及爆破作业等。因此，制定施工方案前先要摸清周边电力设施的实情，如地下电缆的位置和标高，空中架空线路的高度和电压等级，爆破点距离电力设施的距离等等，然后编制施工方案。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]