[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113895":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113895,787,2,"多选题","《中华人民共和国电力法》对用电计量装置的使用规定了（ ）等要求。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","用电计量装置由授权的检定机构进行检定合格",false,{"key":16,"text":17,"correct":18},"B","用电计量装置的设计应征得当地供电部门认可",true,{"key":20,"text":21,"correct":18},"C","施工单位安装完毕应由供电部门检查确认",{"key":23,"text":24,"correct":14},"D","用户在新装、换装及现场校验后，应对用电计量装置加封",{"key":26,"text":27,"correct":14},"E","用电计量装置加封后，供电企业应在工作凭证上签章","BC","2020版教材P339 电力法对用电计量装置使用规定，包括：1）用电计量装置的量值指示是电费结算的主要依据，依据有关法规规定该装置属强制检定范畴，应由省级计量行政主管部门依法授权的检定机构进行检定合格，方为有效。2）用电计量装置的设计应征得当地供电部门认可，施工单位应严格按施工设计图纸进行安装，并符合相关现行国家标准或规范。安装完毕应由供电部门检查确认。3）供电企业在新装、换装及现场校验后应对用电计量装置加封，并请用户在工作凭证上签章。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]