[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113870":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113870,787,2,"多选题","施工记录资料包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","定位放线记录",true,{"key":16,"text":17,"correct":14},"B","特种设备安装检验及验收检验报告",{"key":19,"text":20,"correct":21},"C","分部工程使用功能检测记录",false,{"key":23,"text":24,"correct":21},"D","单位工程质量验收记录",{"key":26,"text":27,"correct":14},"E","隐蔽工程验收记录","ABE","2020版教材P321 本题考查的是竣工验收工作程序和要求。施工记录资料包括：图纸会审记录、设计变更单、隐蔽工程验收记录；定位放线记录；质量事故处理报告及记录；特种设备安装检验及验收检验报告；分项工程使用功能检测记录等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]