[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113869":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113869,787,2,"多选题","施工单位竣工验收的准备工作包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","做好施工项目竣工验收前的收尾工作",true,{"key":16,"text":17,"correct":18},"B","整理汇总技术资料、竣工图，装订成册，分类编目",false,{"key":20,"text":21,"correct":18},"C","核实工程量并评定质量",{"key":23,"text":24,"correct":14},"D","组织相关人员编制竣工结算",{"key":26,"text":27,"correct":14},"E","组织好工程自检","ADE","2020版教材P320 本题考查的是竣工验收工作程序和要求。施工单位竣工验收的准备工作有：（1）做好施工项目竣工验收前的收尾工作；（2）组织技术人员整理竣工资料；（3）组织相关人员编制竣工结算；（4）准备工程竣工通知书、报告、验收证明书、保修证书；（5）组织好工程自检；（6）准备好质量评定的各项资料。 全部验收工作首先要由建设单位会同设计单位、施工单位、监理单位进行验收准备。准备的主要内容有：整理汇总技术资料、竣工图，装订成册，分类编目；核实工程量并评定质量等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]