[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113858":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113858,787,2,"多选题","成本计划的编制方法包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按进度计划编制",false,{"key":16,"text":17,"correct":18},"B","按成本构成编制",true,{"key":20,"text":21,"correct":14},"C","按资源需求编制",{"key":23,"text":24,"correct":18},"D","按项目结构编制",{"key":26,"text":27,"correct":18},"E","按工程实施阶段编制","BDE","2020版教材P286 本题考查的是施工成本控制的依据。成本计划的编制方法包括：按成本构成编制成本计划的方法、按项目结构编制成本计划的方法、按工程实施阶段编制成本计划的方法。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]