[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113843":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113843,787,2,"多选题","合同控制应从（ ）进行，保证合同的顺利履行。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同实施监督",true,{"key":16,"text":17,"correct":18},"B","工程范围控制",false,{"key":20,"text":21,"correct":14},"C","跟踪与调整",{"key":23,"text":24,"correct":14},"D","工程变更管理",{"key":26,"text":27,"correct":18},"E","资金控制","ACD","2020版教材P186 在工程实施的过程中要对合同的履行情况进行合同实施监督、跟踪与调整，并加强工程变更管理，保证合同的顺利履行。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]