[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113838":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113838,787,2,"多选题","作业进度计划的交底内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计划目标和执行计划的相关条件",true,{"key":16,"text":17,"correct":18},"B","施工用人力资源和物资供应保障情况",false,{"key":20,"text":21,"correct":14},"C","计划执行中可能遇见的问题与解决办法",{"key":23,"text":24,"correct":18},"D","各专业队组分工和衔接关系",{"key":26,"text":27,"correct":18},"E","单位工程质量目标","AC","2020版教材P224 本题考查的是施工作业进度计划的实施要求。作业进度计划是项目部在施工期内指导作业的依据，因此计划的编制者应向作业人员进行进度计划交底，交底的内容包括计划目标和执行计划的相关条件，以及计划执行中可能遇见的问题与解决办法，同时对技术措施、质量要求、安全作业等事项提出要求。另：单位工程进度计划交底内容：施工进度控制重点(关键线路、关键工作)、施工用人力资源和物资供应保障情况、各专业队组(含分包方的)分工和衔接关系及时间点、安全技术措施要领和单位工程质量目标。@##",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]