[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113837":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113837,787,2,"多选题","机电工程采用横道图来表示施工进度计划时的优点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","便于实际进度与计划进度比较",true,{"key":16,"text":17,"correct":18},"B","便于看出影响工期的关键工作",false,{"key":20,"text":21,"correct":14},"C","便于计算劳动力的需要量",{"key":23,"text":24,"correct":14},"D","便于计算材料和资金的需要量",{"key":26,"text":27,"correct":18},"E","便于施工进度的动态控制","ACD","2020版教材P221 （2）编制方法简单，直观清晰，便于实际进度与计划进度比较，便于计算劳动力、物资和资金的需要量。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]