[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113836":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113836,787,2,"多选题","下列进度控制措施中，属于经济措施的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","明确工程现场进度控制人员及其分工",false,{"key":16,"text":17,"correct":14},"B","合同中要有专款专用条款，防止因资金问题而影响施工进度",{"key":19,"text":20,"correct":21},"C","施工中及时办理工程预付款",true,{"key":23,"text":24,"correct":21},"D","对工期提前给予奖励",{"key":26,"text":27,"correct":14},"E","施工前应加强图纸审查，严格控制随意变更","CD","2020版教材P229 本题考查的是施工进度控制的主要措施。施工进度控制的主要措施中的经济措施有：（1）在工程预算中考虑加快施工进度所需的资金，编制资金需求计划，满足资金供给，保证施工进度目标所需的工程费用等；（2）施工中及时办理工程预付款及工程进度款支付手续；（3）对应急赶工给予优厚的赶工费用，对工期提前给予奖励，对工程延误收取误期损失赔偿金。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]