[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113835":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113835,787,2,"多选题","机电工程在确定各项工程的开竣工时间和相互搭接关系时，应考虑的因素有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","优先安排工程量大的工业生产主线",true,{"key":16,"text":17,"correct":14},"B","满足机电工程连续均衡施工要求",{"key":19,"text":20,"correct":21},"C","在机电工程施工过程中能加班加点",false,{"key":23,"text":24,"correct":14},"D","考虑各种不利条件的限制和影响",{"key":26,"text":27,"correct":21},"E","考虑各种不利环境的限制和影响","ABD","2020版教材P223 4.在确定各项工程的开竣工时间和相互搭接协调关系时，应考虑以下因素：（1）保证重点、兼顾一般，分清主次，抓住重点，优先安排工程量大的工艺生产主线。（2）满足连续均衡施工要求，使资源得到充分的利用，提高生产率和经济效益。（3）留出一些后备工程，以便在施工过程中作为平衡调剂使用。（4）全面考虑各种不利条件的限制和影响，为缓解或消除不利影响做准备。（5）业主的配合，当地政府有关部门的支持等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]