[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113834":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113834,787,2,"多选题","施工方案的交底内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","进度安排",false,{"key":16,"text":17,"correct":14},"B","组织机构设置",{"key":19,"text":20,"correct":21},"C","施工程序和顺序",true,{"key":23,"text":24,"correct":21},"D","操作方法",{"key":26,"text":27,"correct":21},"E","施工要点","CDE","2020版教材P197 本题考查的是施工技术交底。工程施工前，施工方案的编制人员应向施工作业人员做施工方案的技术交底。除分项、专项工程的施工方案需进行技术交底外，新产品、新材料、新技术、新工艺项目以及特殊环境、特种作业等也必须向施工作业人员交底。交底内容为：施工程序和顺序、施工工艺、操作方法、施工要点、质量控制、安全措施等。 施工组织设计交底的内容包括：工程特点、难点、主要施工工艺及施工方法、进度安排、组织机构设置与分工及质量、安全技术措施等。@##",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]