[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113831":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113831,787,2,"多选题","施工组织设计交底的内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程特点、难点",true,{"key":16,"text":17,"correct":14},"B","主要施工工艺及施工方法",{"key":19,"text":20,"correct":14},"C","进度安排",{"key":22,"text":23,"correct":14},"D","安全技术措施",{"key":25,"text":26,"correct":27},"E","操作方法",false,"ABCD","2020版教材P209 （2）施工组织设计交底。工程开工前，施工组织设计的编制人员应向施工人员作施工组织设计交底，以做好施工准备工作。施工组织设计交底的内容包括：工程特点、难点、主要施工工艺及施工方法、进度安排、组织机构设置与分工及质量、安全技术措施等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]