[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113825":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113825,787,2,"多选题","在材料进场时，项目部进行材料数量和质量验收的依据有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","送料凭证",true,{"key":16,"text":17,"correct":14},"B","进料计划",{"key":19,"text":20,"correct":21},"C","施工图纸",false,{"key":23,"text":24,"correct":21},"D","用料计划",{"key":26,"text":27,"correct":14},"E","质量保证书","ABE","2020版教材P203 在材料进场时必须根据进料计划、送料凭证、质量保证书或产品合格证，进行材料的数量和质量验收；",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]