[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113822":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113822,787,2,"多选题","施工方案编制的内容中应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工安排",true,{"key":16,"text":17,"correct":18},"B","工程索赔程序",false,{"key":20,"text":21,"correct":14},"C","施工进度计划",{"key":23,"text":24,"correct":18},"D","费用控制措施",{"key":26,"text":27,"correct":14},"E","质量安全保证措施","ACE","2020版教材P195 编制内容包括工程概况、编制依据、施工安排、施工进度计划、施工准备与资源配置计划、施工方法及工艺要求、质量安全保证措施等基本内容。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]