[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113817":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113817,787,2,"多选题","金属排水管道上的吊钩或卡箍应固定在承重结构上，固定件间距是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","横管不大于3m",false,{"key":16,"text":17,"correct":14},"B","立管不大于4m",{"key":19,"text":20,"correct":21},"C","楼层高度小于或等于4m时，每层必须安装1个固定件",true,{"key":23,"text":24,"correct":21},"D","立管底部的弯管处应设支墩或采取固定措施",{"key":26,"text":27,"correct":14},"E","楼层高度大于5m时，每层不得少于2个固定件","CD","2020版教材P132 金属排水管道上的吊钩或卡箍应固定在承重结构上，固定件间距是横管不大于2m，立管不大于3m，楼层高度小于或等于4m时，每层必须安装1个固定件，立管底部的弯管处应设支墩或采取固定措施",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]