[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113816":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113816,787,2,"多选题","在管线测量前，安装单位应进行测量基准的交接的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","土建单位",false,{"key":16,"text":17,"correct":14},"B","测绘单位",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":21},"D","监理单位",{"key":26,"text":27,"correct":14},"E","以上全部","CD","2020版教材P130 测量前应与建设单位（或监理单位）进行测量基准的交接。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]