[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113815":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113815,787,2,"多选题","室内给水管道的安装工艺流程中，管道安装后的工序有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管道支架安装",false,{"key":16,"text":17,"correct":18},"B","防腐绝热",true,{"key":20,"text":21,"correct":14},"C","管道支管安装",{"key":23,"text":24,"correct":18},"D","系统压力试验",{"key":26,"text":27,"correct":18},"E","系统清洗、消毒","BDE","2020版教材P128 室内给水管道施工程序，管道安装以后的流程是：管道安装，系统压力试验，防腐绝热，系统清洗、消毒，系统通水试验",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]