[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113810,787,2,"多选题","安装在主干管上起切断作用的闭路阀门，应逐个做（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","严密性试验",true,{"key":16,"text":17,"correct":14},"B","强度试验",{"key":19,"text":20,"correct":21},"C","通水试验",false,{"key":23,"text":24,"correct":21},"D","灌水试验",{"key":26,"text":27,"correct":21},"E","通球试验","AB","2020版教材P130 安装在主干管上起切断作用的闭路阀门，应逐个做强度试验和严密性试验。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]