[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113777":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113777,787,2,"多选题","消防验收的顺序包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","验收受理",true,{"key":16,"text":17,"correct":14},"B","现场检查",{"key":19,"text":20,"correct":14},"C","现场验收",{"key":22,"text":23,"correct":24},"D","隐蔽工程验收",false,{"key":26,"text":27,"correct":14},"E","结论评定","ABCE","2020版教材P169 （2）验收顺序通常为验收受理、现场检查、现场验收、结论评定和工程移交等阶段。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]