[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113770":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113770,787,2,"多选题","电动风阀控制器安装前应进行的检查内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","线圈和阀体间电阻",true,{"key":16,"text":17,"correct":18},"B","驱动速度",false,{"key":20,"text":21,"correct":14},"C","供电电压",{"key":23,"text":24,"correct":18},"D","负载电流",{"key":26,"text":27,"correct":14},"E","输入信号","ACE","2020版教材P158 电动风阀控制器安装前，应检查线圈和阀体间的电阻，供电压，输入信号否符合要求，宜进行模拟动作检查",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]