[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113752":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113752,787,2,"多选题","下列现场安装条件中，高效过滤器安装前必备的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","洁净室的内装修工程全部完成",true,{"key":16,"text":17,"correct":14},"B","洁净室已经全面清扫、擦拭、空吹12～24h",{"key":19,"text":20,"correct":14},"C","高效过滤器已在洁净室外拆除外包装",{"key":22,"text":23,"correct":24},"D","洁净室的洁净度已达到设计要求",false,{"key":26,"text":27,"correct":14},"E","高效过滤器已经扫描检漏，且达到合格","ABCE","2020版教材P151 高效过滤器安装前，洁净室的内装修工程必须全部完成。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]