[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113751":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113751,787,2,"多选题","风管系统安装完后，对风管进行严密性检验的主要部位有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","咬口缝",true,{"key":16,"text":17,"correct":18},"B","板材",false,{"key":20,"text":21,"correct":14},"C","铆接孔",{"key":23,"text":24,"correct":14},"D","法兰翻边",{"key":26,"text":27,"correct":14},"E","管段连接处","ACDE","2020版教材P148 风管系统安装完后，应对安装后的主，干风管分段进行严密性试验。严密性试验，主要检验风管，部件制作加工后的咬口缝，铆接孔，风管的法兰翻边，风管管段之间的连接严密性，检验合格后方能交付下道工序。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]