[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113748":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113748,787,2,"多选题","风管安装就位的程序通常为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先上层后下层",true,{"key":16,"text":17,"correct":18},"B","先下层后上层",false,{"key":20,"text":21,"correct":14},"C","先立管后水平管",{"key":23,"text":24,"correct":14},"D","先主干管后支管",{"key":26,"text":27,"correct":18},"E","先支管后主干管","ACD","2020版教材P147 本题考查的是通风空调风管系统的技术要求。风管安装就位的程序通常为：先上层后下层，先主干管后支管，先立管后水平管。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]