[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113737":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113737,787,2,"多选题","洁净空调工程调试前，通风空调系统运转所需的（ ）等已具备。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","用水",true,{"key":16,"text":17,"correct":14},"B","用电",{"key":19,"text":20,"correct":21},"C","油路通",false,{"key":23,"text":24,"correct":14},"D","用汽",{"key":26,"text":27,"correct":14},"E","压缩空气","ABDE","2020版教材P151 4、洁净空调工程调试要点洁净空调工程调试前，洁净室各分部工程的外观检查已完成，且符合合同和规范的要求，通风空调系统运转所需用的水、电、汽及压缩空气等已具备。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]