[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113734":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113734,787,2,"多选题","通风空调设备试运行调试时间符合规定的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","风机连续运转2h",true,{"key":16,"text":17,"correct":14},"B","水泵连续运转2h",{"key":19,"text":20,"correct":21},"C","冷却水系统循环试运行不少于8h",false,{"key":23,"text":24,"correct":14},"D","制冷机组试运转不少于8h",{"key":26,"text":27,"correct":21},"E","通风系统的连续试运行应不少于8h","ABD","2020版教材P150 本题考查的是通风与空调工程施工程序。选项C错误，冷却塔风机与冷却水系统循环试运行不少于2h；选项E错误，通风系统的连续试运行不应少于2h。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]