[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113705":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113705,787,2,"多选题","工业炉窑砌筑工程工序交接证明书中，合格证明主要包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管道和炉壳的试压记录",true,{"key":16,"text":17,"correct":14},"B","管道和炉壳的焊接严密性试验",{"key":19,"text":20,"correct":21},"C","静态式炉窑试运转",false,{"key":23,"text":24,"correct":21},"D","炉体冷却装置试运转",{"key":26,"text":27,"correct":14},"E","炉子可动部分的试运转","ABE","2020版教材P122 本题考查的是炉窑砌筑前工序交接的规定。工序交接证明书应包括的内容：炉子中心线和控制标高的测量记录及必要的沉降观测点的测量记录；隐蔽工程的验收合格证明；炉体冷却装置、管道和炉壳的试压记录及焊接严密性试验合格证明；钢结构和炉内轨道等安装位置的主要尺寸复测记录；动态炉窑或炉子的可动部分试运转合格证明；炉内托砖板和锚固件等的位置、尺寸及焊接质量的检查合格证明；上道工序成果的保护要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]