[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113688":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113688,787,2,"多选题","设备、管道隔热层的金属保护层施工中，（ ）要求将其金属保护层分段固定在支承件上。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","支座距离大的卧式设备",false,{"key":16,"text":17,"correct":18},"B","立式设备",true,{"key":20,"text":21,"correct":18},"C","垂直管道",{"key":23,"text":24,"correct":18},"D","斜度大于45°的斜立管道",{"key":26,"text":27,"correct":14},"E","大跨度水平管道","BCD","2020版教材P119 10.立式设备、垂直管道或斜度大于45°的斜立管道上的金属保护层，应分段将其固定在支承架件上。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]