[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113662":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113662,787,2,"多选题","分段到货塔器如炼油装置的分离塔，其组对安装方式主要有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","卧装",true,{"key":16,"text":17,"correct":14},"B","由下至上逐段组对安装",{"key":19,"text":20,"correct":21},"C","散装",false,{"key":23,"text":24,"correct":21},"D","倒装",{"key":26,"text":27,"correct":21},"E","顶升法组对安装","AB","2020版教材P100 分段安装方法，采用卧装法或立式正装方施工",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]