[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113657":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113657,787,2,"多选题","关于工业小型汽轮机转子安装技术要点的说法中，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","转子安装可以分为转子吊装、转子测量和转子、汽缸找中心",true,{"key":16,"text":17,"correct":18},"B","低压缸排汽口与凝汽器采用刚性中间连接段连接",false,{"key":20,"text":21,"correct":14},"C","转子吊装应使用有制造厂提供并具备出厂试验证书的专用横梁和吊索",{"key":23,"text":24,"correct":14},"D","汽轮机正式扣盖之前，应将内部零部件全部装齐后进行试扣",{"key":26,"text":27,"correct":14},"E","转子测量应包括：轴颈圆度、圆柱度的测量、转子跳动测量（径向、端面和推力盘不平度）、转子水平度测量","ACDE","2020版教材P88 （4）转子安装技术要点1）转子安装可以分为：转子吊装、转子测量和转子、汽缸找中心。2）转子吊装应使用有制造厂提供并具备出厂试验证书的专用横梁和吊索，否则应进行200%的工作负荷试验（时间为1h）。3）转子测量应包括：轴颈圆度、圆柱度的测量、转子跳动测量（径向、端面和推力盘不平度）、转子水平度测量。 @##",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]