[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113656":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113656,787,2,"多选题","发电机转子安装技术要点包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","转子穿装后进行单独气密性试验",false,{"key":16,"text":17,"correct":18},"B","气密性试验消除泄漏后，应再经漏气量试验",true,{"key":20,"text":21,"correct":18},"C","在完成机务、电气与热工仪表的各项工作后穿转子",{"key":23,"text":24,"correct":18},"D","对定子和转子进行最后清扫检查",{"key":26,"text":27,"correct":14},"E","转子穿装方法按设计要求进行","BCD","2020版教材P90 本题考查的是发电机的安装技术要求。选项A，在转子穿装前要进行气密性试验；选项E，转子穿装方法按制造厂说明书的要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]