[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113650":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113650,787,2,"多选题","汽轮机台板，气缸、轴承座安装的质量控制点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","气缸纵横中心线、标高",true,{"key":16,"text":17,"correct":18},"B","垫铁安装位置合理",false,{"key":20,"text":21,"correct":14},"C","二次灌浆强度",{"key":23,"text":24,"correct":14},"D","二次灌浆密实情况",{"key":26,"text":27,"correct":18},"E","油系统管道清洁、畅通","ACD","2020版教材P87 2）台板，汽缸、轴承座安装：汽缸纵横中心线，标高等，二次灌浆的强度、密实情况，确保上下部件联结和受热膨胀不致受阻，机器精找正、找和联轴器对中后机器底部与基础之间的灌浆强度。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]