[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113647":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113647,787,2,"多选题","汽轮机设备本体安装的主要内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查汽缸、转子、主汽阀等零部件",false,{"key":16,"text":17,"correct":18},"B","凝汽器的安装",true,{"key":20,"text":21,"correct":18},"C","汽缸的就位和找中",{"key":23,"text":24,"correct":18},"D","转子就位、流通间隙调整、上下汽缸闭合安装",{"key":26,"text":27,"correct":14},"E","蒸汽管道吹扫液压轴系统冲洗","BCD","2020版教材P86 2.汽轮机本体的安装:包括凝汽器的安装、汽缸、台板和轴承座的就位、汽缸的就位和找中、隔板的就位和找中、轴承找中、转子就位、通流间隙调整、上下汽缸闭合安装、汽缸下部汽管道连接等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]