[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113633":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113633,787,2,"多选题","管道系统真空度试验的实施要点包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","所有管道必须进行真空度试验",false,{"key":16,"text":17,"correct":14},"B","真空度试验主要检验管道系统的强度",{"key":19,"text":20,"correct":14},"C","真空度试验在液压试验合格后进行",{"key":22,"text":23,"correct":24},"D","按设计文件规定进行24h试验",true,{"key":26,"text":27,"correct":24},"E","24h后增压率不大于5%","DE","2020版教材P84 本题考查的是管道系统试验。选项A：只有真空系统才需要做真空度试验；选项B：真空度试验主要检验管道系统的严密性；选项C：真空度试验在气压试验合格后进行。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]