[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113631":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113631,787,2,"多选题","有关管道支、吊架安装要求，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","固定支架应按设计文件的规定安装",true,{"key":16,"text":17,"correct":18},"B","固定支架固定前进行补偿器预拉伸",false,{"key":20,"text":21,"correct":14},"C","无热位移的管道，其吊杆应垂直安装",{"key":23,"text":24,"correct":18},"D","有热位移的管道，吊点沿位移方向偏位1\u002F2安装",{"key":26,"text":27,"correct":14},"E","弹簧的临时固定件待绝热完毕后拆除","ACE","2020版教材P81 本题考查的是工业管道施工的技术要求。选项B，固定支架应按设计文件要求或标准图安装，并应在补偿器预拉伸之前固定；选项D，有热位移的管道，吊点应设在位移的相反方向，按位移值的1\u002F2偏位安装。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]