[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113629":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113629,787,2,"多选题","下列实测数据中，符合卷管制作要求的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","同一筒节两纵焊缝距离为200mm",true,{"key":16,"text":17,"correct":18},"B","两节组对时，相邻筒节两纵焊缝间距100mm",false,{"key":20,"text":21,"correct":14},"C","加固环对接缝与管子纵焊缝错开120mm",{"key":23,"text":24,"correct":14},"D","卷管端面与中心线的垂直允许偏差为管子外径的8‰",{"key":26,"text":27,"correct":18},"E","每米直管的平直度偏差为1.5mm","ACD","2020版教材P77 本题考查的是工业管道施工的技术要求。卷管制作要求：（1）卷管同一筒节两纵焊缝间距不应小于200mm；（2）卷管组对时，相邻筒节两纵焊缝间距应大于100mm；（3）有加固环、板的卷管，其对接焊缝应与管子纵向焊缝错开，其间距不应小于100mm，加固环、板距卷管的环焊缝不应小于50mm；（4）卷管端面与中心线的垂直允许偏差不得大于管子外径的1%，且不得大于3mm，每米直管的平直度偏差不得大于1mm。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]