[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113623":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113623,787,2,"多选题","弹簧支、吊架中弹簧的临时固定件，如定位销等，应待系统（ ）完毕后方可拆除。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","安装",true,{"key":16,"text":17,"correct":18},"B","检查",false,{"key":20,"text":21,"correct":14},"C","试压",{"key":23,"text":24,"correct":18},"D","冲洗",{"key":26,"text":27,"correct":14},"E","绝热","ACE","2020版教材P81 （4）弹簧支、吊架的弹簧高度，应按设计文件规定安装，弹簧应调整至冷态值，并做记录。弹簧的临时固定件，如定位销（块），应待系统安装、试压、绝热完毕后方可拆除。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]