[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113610":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113610,787,2,"多选题","架空线路试验内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","测线路的绝缘电阻",true,{"key":16,"text":17,"correct":18},"B","交流耐压试验",false,{"key":20,"text":21,"correct":14},"C","冲击合闸试验",{"key":23,"text":24,"correct":14},"D","测量杆塔的接地电阻值",{"key":26,"text":27,"correct":18},"E","泄露电流试验","ACD","2020版教材P64 本题考查的是电力架空线路施工要求。架空线路试验包括：（1）测量线路的绝缘电阻应不小于验收规范规定；（2）检查架空线各相的两侧相位应一致；（3）在额定电压下对空载线路的冲击合闸试验应进行3次；（4）测量杆塔的接地电阻值应符合设计的规定；（5）导线接头测试可采用红外线测温仪，通过导线接头温度的测量，来检验接头的连接质量。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]