[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113607":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113607,787,2,"多选题","电气装置通电检查及调整试验的具体内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先一次回路通电检查，后二次回路检查",false,{"key":16,"text":17,"correct":18},"B","继电器和仪表等均经校验合格",true,{"key":20,"text":21,"correct":14},"C","电流互感器二次侧无短路现象",{"key":23,"text":24,"correct":18},"D","电压互感器二次侧无短路现象",{"key":26,"text":27,"correct":18},"E","回路经过绝缘电阻测定和耐压试验，绝缘电阻值均符合规定","BDE","2020版教材P60 本题考查的是电气设备的施工技术要求。先二次回路通电检查，后一次回路检查；电流、电压互感器已经过电气试验，电流互感器二次侧无开路现象，电压互感器无短路现象。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]