[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113605":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113605,787,2,"多选题","油浸电力变压器的一般施工程序中，变压器就位后的工序有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","绝缘测试",false,{"key":16,"text":17,"correct":14},"B","器身检查",{"key":19,"text":20,"correct":21},"C","附件安装",true,{"key":23,"text":24,"correct":21},"D","滤油注油",{"key":26,"text":27,"correct":14},"E","通电运行","CD","2020版教材P57 油浸电力变压器的一般施工程序为：开箱检查→二次搬运→设备就位→吊芯检查→附件安装→滤油、注油→交接试验→验收。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]