[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113596":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113596,787,2,"多选题","组织新建电气系统供电，应按（ ）的顺序通电",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各系统同时试通电",false,{"key":16,"text":17,"correct":18},"B","先高压后低压",true,{"key":20,"text":21,"correct":18},"C","先干线后支线",{"key":23,"text":24,"correct":14},"D","通电正常后进行交接试验",{"key":26,"text":27,"correct":14},"E","先支线后干线","BC","2020版教材P60 （2）按已批准的受电作业指导书，组织新建电气系统变压器高压侧接受电网侧供电，通过配电柜按先高压后低压、先干线后支线的原则逐级试通电。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]