[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113587":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113587,787,2,"多选题","成套配电设备的安装要求包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基础型钢的两端与接地干线应焊接牢固",true,{"key":16,"text":17,"correct":18},"B","柜体间及柜体与基础型钢间应焊接固定",false,{"key":20,"text":21,"correct":14},"C","成列安装柜体时，宜从中部开始向两边安装",{"key":23,"text":24,"correct":18},"D","手车推进时接地触头比主触头后接触",{"key":26,"text":27,"correct":14},"E","同一功能单元、同一种型式的高压电器组件能互换使用","ACE","2020版教材P59 本题考查的是电气设备的施工技术要求。选项B，柜体间及柜体与基础型钢的连接应牢固，不应焊接固定。选项D，手车推进时接地触头比主触头先接触，手车拉出时接地触头比主触头后断开。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]