[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113582":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113582,787,2,"多选题","油浸式电力变压器是否需要吊芯检查，应根据（ ）而确定。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","变压器的大小",true,{"key":16,"text":17,"correct":14},"B","制造厂规定",{"key":19,"text":20,"correct":14},"C","存放时间",{"key":22,"text":23,"correct":14},"D","运输过程中有无异常",{"key":25,"text":26,"correct":27},"E","耐压试压结果",false,"ABCD","2020版教材P57 本题考查的是电气安装程序。油浸式电力变压器是否需要吊芯检查，应根据变压器的大小、制造厂规定、存放时间和运输过程中有无异常和建设单位要求而确定。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]