[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113560":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113560,787,2,"多选题","机械设备安装设定基准线和基准点应遵循的原则有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","安装检测使用方便",true,{"key":16,"text":17,"correct":14},"B","有利于保持而不被摧毁",{"key":19,"text":20,"correct":21},"C","不宜设在同一基础上",false,{"key":23,"text":24,"correct":21},"D","关联设备不应相互采用",{"key":26,"text":27,"correct":14},"E","刻划清晰内容易识别","ABE","2020版教材P49 本题考查的是机械设备安装的一般程序和一般要求。设定基准线和基准点，通常应遵循原则的有：安装检测使用方便；有利于保护而不被毁损；刻画清晰容易辨识。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]