[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113556":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113556,787,2,"多选题","设备就位前，应经检查确认下列工作（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设备运至安装现场经开箱检查验收合格",true,{"key":16,"text":17,"correct":14},"B","除去设备底面的泥土、油污",{"key":19,"text":20,"correct":21},"C","设备基础沉降预压试验合格",false,{"key":23,"text":24,"correct":21},"D","二次灌浆强度足够",{"key":26,"text":27,"correct":21},"E","垫铁间已点焊固定","AB","2020版教材P52 本题考查的是机械设备安装的一般程序和一般要求。设备就位前，应经检查确认下列工作：（1）设备运至安装现场经开箱检查验收合格；（2）设备基础经检验合格，混凝土基础达到强度；（3）除去设备底面的泥土、油污、与混凝土（含二次灌浆）接触部位油漆；（4）二次灌浆部位的设备基础表面凿成麻面且不得有油污；（5）清除混凝土基础表面浮浆、地脚螺栓预留孔内泥土杂物和积水；（6）垫铁和地脚螺栓按技术要求准备并放置。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]