[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113551":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113551,787,2,"多选题","长距离输电线路钢塔架的中心桩测定后，一般采用（ ）进行控制。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","十字线法",true,{"key":16,"text":17,"correct":14},"B","平行基线法",{"key":19,"text":20,"correct":21},"C","电磁波测距法",false,{"key":23,"text":24,"correct":21},"D","激光仪测量法",{"key":26,"text":27,"correct":21},"E","解析法","AB","2020版教材P24 本题考查的是机电工程中常见的工程测量。长距离输电线路定位并经检查后，可根据起、止点和转折点及沿途障碍物的实际情况，测设钢塔架基础中心桩，其直线投点允许偏差和基础之间的距离丈量允许偏差应符合规定。中心桩测定后，一般采用十字线法或平行基线法进行控制，控制桩应根据中心桩测定，其允许偏差应符合规定。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]