[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113543":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113543,787,2,"多选题","在钢塔架基础中心桩测定后，控制桩应根据中心桩测定，一般采用（ ）进行控制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","十字线法",true,{"key":16,"text":17,"correct":18},"B","高差法",false,{"key":20,"text":21,"correct":18},"C","仪高法",{"key":23,"text":24,"correct":14},"D","平行基线法",{"key":26,"text":27,"correct":18},"E","叠加法","AD","2020版教材P24 中心桩测定后，一般采用十字线法或平行基线法进行控制，控制粧应根据中心桩测定，其允许偏差应符合规定。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]